Cat B fit-out of the 5th Floor at 1 London Bridge including an internal refresh of the existing 4th-floor offices.
The works to both floors were undertaken in parallel, with the 4th floor being fully occupied, therefore all works were completed out of hours. This was a full Design & Build contract, completed within a fast program of just 9 weeks. To ensure that the client could move in prior to the Christmas shut down, we also reduced the programme duration by a further week.
The long lead items were critical to the project, new VAV units, bespoke tiles, and a fabricated SAS ceiling tile system. Early coordination workshops were held to fully understand the M&E scope and flooring specification to ensure early procurement.
Refurbishment works included the relocation of existing VAV’s as well as installation of supplementary units, electrical modifications, new floor finishes, drywall & glass partitions, decorations, new tea point, and bespoke storage units.